19 November 2005

Working Party Report

Category: Longhoughton — dmshell @ 12:00 am

Longhoughton Goods Yard - ?, general stock maintenance - futher details to be confirmed, The lower halves of the axle boxes on the Ruston were removed so the oil
reservoirs can be cleaned out and the oiler pads checked.Drain holes were drilled in the crane frame and a temporary wooden cover has
been constructed over the gears on the crane to try and protect them from
the winter weather.

Bad Behavior has blocked 109 access attempts in the last 7 days.