4 March 2006

Working Party Report

Category: Longhoughton — dmshell @ 12:00 am

- BS, DMS, Despite the snow the workday took place. The Jones crane has been delivered to site, and a start was made on stripping the mechanisms in order that they can be freed and cleaned up. We also had a look at the large crane to try and solve the slewing issue. The main problem has been identified – a collar that carries the rollers for the main body is seized solid.

Bad Behavior has blocked 111 access attempts in the last 7 days.