Longhoughton Goods Yard - KSW, SY, RJ, TS, continuation of general tasks as required, Tom replaced missing grease nipple on 37995 linkage and put that back together. Scott cleaned arm of ditcher and started painting, ready for return of cylinders. Kay and Tom placed two more sleepers on Clockwork Ruston’s panel and used 37995 to move Ruston along (next time, remember to take chocks out first) so she’s now sitting safely on panel. Roland continued work on crane - I don’t think it will hold out much longer against this sustained attack.