21 July 2007
Working Party Report
Longhoughton Goods Yard - KM, BS, DMS, TS, KSW, DT, IC, MH, laying out sidings; cleaning the Mk 1 roof; rubbing down Mk 1 sides; rewiring 48DS; check over rail crane; moving materials; tidying access road and yard, Two of the Permaquip B trolleys were unloaded and lifted over onto road 2. The crane was used to lift the van body and the trolleys were put underneath and then they were pushed up to south end of the siding. the crane was then pushed up seperatley. With a bit of lifting and slewing the van was positioned as close as possible to the designated site, and then pushed over with pinch bars.