8 December 2007
Working Party Report
Longhoughton Goods Yard - BS, DMS, KSW, MH, IC, Baz moved the Atlas to the middle of the yard and greased ALL points, while Dave topped up the Hydraulic levels. Dave and Mark had a look at the electrics on DX 98707 and we have progressed a little bit further. Dave and Mark then went to collect the Kango genny and hammers. The genny has been started and runs fine. Baz and Ian lifted in two 30ft BH rails to extend road 1. Baz, Dave and Ian then keyed up these rails. Kay spent the day fitting more flooring to the mark 2s.At around 14:15 it was declared “Rain stops play” and we packed up for the day.