26 January 2008

Working Party Report

Category: Longhoughton — dmshell @ 12:00 am

Longhoughton Goods Yard - , recovering track components from panel stacks and preparing space for arrival of more materials,

19 January 2008

Working Party Report

Category: Longhoughton — dmshell @ 12:00 am

Longhoughton Goods Yard - DMS, RJ, MH, TBA, Dave used the Atlas to move the remaining sleepers from the stripped panels to a rough stockpile. Roland was then shown the basic of the Atlas. Mark arrived and we picked up some benches that had been saved from the skip by Roland. Roland then used the Atlas to level of the land near the dogleg in the yard boundary, thus giving a bit more level space for materials.

12 January 2008

Working Party Report

Category: Longhoughton — dmshell @ 12:00 am

Longhoughton Goods Yard - BS, DMS, MH, AH, a tidy up. I have un-keyed a few more rails on the stacks so these can be lifted down. There are still some small track components at the south end to bag up. If the wind is light as suggested it may be an idea to modify the sheets for the Mk 2 BFK., Baz and Dave S arrived and made a start on picking up rubbish from around the site. The Atlas was then fired up and used to lift the out of profile rail out from road 1. The other lengths were also lifted out and moved to stockpile. The sleepers were then moved out the way, to give access to a pile of spoil that has been dropped in this area during earlier (Easter?) earthworks and landscaping. This was re-graded, and a number of rail chairs that had been left here were recovered. A start was then made on dismantling the panels in the back stack (the one that was trapped behind the ballast wagon before we moved this), and this continued throughout the day, with the assistance of Mark and Alistair.

5 January 2008

Working Party Report

Category: Longhoughton — dmshell @ 12:00 am

Longhoughton Goods Yard - BS, DMS, KM, TS, DT, IC, NB, recovering track components from panel stacks and inserting rails into road 1, Baz & Dave S arrived and started by firing up the Atlas and moving the sheets for use later in the day. Baz then lifted the rail out of the top panel on stack 1 and moved these to the stockpile. The sleepers were then lifted down and laid out in the gap in Road #1. The next set of rails from stack 1 were then lifted down and dropped into the gap on Road #1. It transpired that one rail was too long so an alternative rail was sourced from another panel. The rails were then turned in and keyed up. The small gap on one side was bridged, and the ballast wagon was then moved over onto road 1 ext to DX98702. This brought us up to the lunch break. After lunch Dave measured up some more panels. Baz, Ian, Tom & Dave T prepared the sheets to go over the Mark 2s. Kay continued work inside the TSO. Kenny delivered some more materials for the GVB. The 110v genny was fired up in the late afternoon to provide some light – and a minor tidy up was undertaken too.

Bad Behavior has blocked 82 access attempts in the last 7 days.